
Contractors on Virginia public projects likely are aware that their responsibility to correct defective construction can be unending. By Virginia statute (Code §8.01-231), there is no statute of limitations that applies against the Commonwealth. While private parties are barred from bringing lawsuits after a certain period of time, no such bar applies to the Commonwealth.
This month the Supreme Court of Virginia made clear in Hensel Phelps Construction v. Thompson Masonry Contractor that incorporating the prime contract on a state project into lower tier subcontracts is not enough to also expose the lower-tier subcontractors to endless liability. The endless period isn’t created by the prime contract, but by the statute.
Fourteen years after finishing a job at Virginia Tech, the Commonwealth sued Hensel Phelps for defective work. Hensel Phelps settled and then sought to recover from its subs. Hensel Phelps asserted defective work claims, for which the time period to sue began when the breach (i.e. defective work) occurred. The trial court dismissed the lawsuit, finding that as between Hensel Phelps and the subs, the statute of limitations for breach of contracts had expired and barred the recovery claims. The Supreme Court agreed.
Hensel Phelps may have succeeded in pursuing claims against the subs had the indemnity provisions of its subcontracts been enforceable. Claims for indemnity do not begin to run until the indemnitee pays the obligation for which it is owed indemnity. Under that theory, the indemnity claim didn’t arise until Hensel Phelps paid the settlement.
Unfortunately for Hensel Phelps, the indemnity clauses in its subcontracts were too broad. The clauses attempted to indemnify Hensel Phelps even for its own negligence: running afoul of Virginia law holding indemnification void as against public policy where it indemnifies a party against liability for his own negligence.
This case gives rise to several important lessons learned:
Be aware that public projects can carry endless liability;
Make sure your indemnity clauses are drafted so as to be enforceable under all law;
When working on public projects, carefully review whether your contract lines up with the recovery rights you seek to preserve.For instance, general contractors could require subcontractors to expressly waive any rights under the statute of limitations.
Consider including language explaining the rights among the parties in the event of future recovery actions by a public owner, such as delayed accrual for indemnity claims or affirmative rights to assert breaches long after a statute of limitations has expired.
As president of Hirschler and head of the firm's litigation section, Courtney knows how to lead people and projects to a successful outcome.
Leveraging deep experience in the construction industry, Courtney advises public and ...
Kelly’s practice focuses on construction law, commercial and product liability law, with an emphasis on dispute resolution—including mediation, arbitration, jury and bench trials in state and federal court. She routinely ...
Nate fully engages in each case and shoulders his clients’ needs. Communication, efficiency and careful judgment define his practice. In every case, he investigates competing claims to thoroughly understand their strengths ...
A professional engineer (P.E.) and an experienced lawyer, Webb began practicing at Hirschler Fleischer following four years of work as a consulting engineer. His multidisciplinary practice focuses on general business and ...
Subscribe
Subscribe to Hirschler by EmailRecent Posts
- OSHA Increases Amounts of Civil Penalties for 2021
- Have Force Majeure Defenses Based on COVID-19 Been Successful This Year?
- Kelly Bundy and Liz Burneson Publish Article on Joint Employer Status in Construction Executive
- Kelly Bundy Authors Article for ABA Construction Law Forum’s “Under Construction” Series
- Miller Act Notice More Than 90 Days Before A Subcontractor’s Final Day of Work Held Untimely
- Virginia Supreme Court Allows Sub-Sub Material Supplier To Recover Directly From General Contractor For Unpaid Material
- New Virginia Law Can Make General Contractors Liable for Subcontractors' Employee Wages
- OSHA Changes Course on COVID-19 Record-Keeping Requirements
- New OSHA Guidance Suspends Enforcement of Record-Keeping Requirements for COVID-19 Cases in Most Industries
- What the Virginia Temporary Stay at Home Order Means for Your Business
Popular Topics
- Contracts
- Occupational Safety and Health Act (OSHA)
- Safety
- Legislation
- COVID-19, Coronavirus Outbreak
- Indemnification
- Litigation
- Department of Labor (DOL)
- Employment
- Records
- Little Miller Act
- Dispute Resolution
- Miller Act
- Government Contracts
- Workforce Development
- Mechanic's Liens
- Procurement
- Department of Professional and Occupational Regulation (DPOR)
- Force Majeure
- Payment
- Environmental
- Damages
- Delays
- Tax
- Insurance
- Subrogation
- Licenses
- Joint Checks
- Unjust Enrichment
- Negligence
- Arbitration
- Mediation
- Scheduling
- Suretyship
- Virginia Employment Commission (VEC)
- Virginia Workers' Compensation Commission
- Uniform Statewide Building Code
- Change Orders
Contributors
Archives
- January 2021
- October 2020
- August 2020
- July 2020
- June 2020
- May 2020
- April 2020
- March 2020
- February 2020
- January 2020
- November 2019
- August 2019
- June 2019
- April 2019
- February 2019
- January 2019
- December 2018
- October 2018
- September 2018
- June 2018
- May 2018
- April 2018
- March 2018
- February 2018
- November 2017
- October 2017
- September 2017
- July 2017
- June 2017
- May 2017
- April 2017
- March 2017
- February 2017
- January 2017
- December 2016
- November 2016
- October 2016